400-650-7353
登录 | 注册
您当前的位置 > 中公PMP培训 > 模拟试题 > 2021PMP考试单元测试一

2021PMP考试单元测试一

  • 发布: 中公PMP培训机构
  • 来源:PMP培训
  • 2021-02-25 10:42:45
  • 阅读()
  • 分享

1. Market dynamics have changed. The project sponsor wants to terminate the project because of its uncertain performance. What should the project manager and the project sponsor review?

市场动态发生变化。由于项目绩效不确定,项目发起人希望终止项目。项目经理和项目发起

人应审查什么?

A. A root cause analysis and an action plan for the technical issues

根本原因分析和技术问题的行动计划

B. Project's technical and commercial goals, viability, and profitability

项目的技术和商务目标,可行性和盈利性

C. A change request to modify the project requirements

修订项目需求的变更请求

D. Explanations of the processes that caused the technical issues

对导致技术问题的过程进行解释

 

2. What is the main objective of the Executing Process group?

执行过程组的主要目标是什么?

A. Tracking and reviewing the progress of the project

跟踪并审查项目进度

B. Managing stakeholder expectations

管理利害关系者的期望

C. Satisfying the project specifications

满足项目规范

D. Monitoring the schedule

监控进度表

 

3. Which of the following statements reflect the degree of risk to the project?

下列哪项陈述反映了项目的风险程度?

A. Risk is greatest at the beginning of the project.

项目初始阶段的风险最大。

B. Risk is least at the beginning of the project.

项目初始阶段的风险最小。

C. Risk is constant throughout the project.

风险在整个项目期间保持恒定。

D. Risk is greatest during the implementation of the project.

项目实施过程中的风险最大。
 

 

参考答案

1.答案:B,项目终止的原因包括目标实现了,目标消失了(不符合公司战略),目标不可能实

现了(没有资金了)

2.答案:C,执行过程组包含完成项目管理计划中确定的工作以实现项目目标的一组过程。这个过程组不但要协调人员和资源,还要按照项目管理计划整合并实施项目活动

3.答案:A,项目风险在初始阶段最大.根据答案判断,AB 两个选项为相反选项,因此答案必定从 AB 中进行选择,根据判断,此题很容易得到答案 A

>>本文地址:
注:本站稿件未经许可不得转载,转载请保留出处及源文件地址。